| No. | Name | Name (Eng) | Scheduled delivery date | Delivery start date | Incoterms code | Destination country | Delivery region | OKTMO Code | OKEI code | Quantity | Unit of measure | Number of bidders |
| 1 | Piping products 4 QNC DN<100 | Turbine building (10UMA). Pipelines of secondary circuit equipment and pipelines hydraulic tests system PoP<2.2 Mpa RPR.0903.00UMA.LWB.TM.EC.2925. | 01.12.2024 | 01.12.2024 | DAP | RU | — | 22000000 | 166 | 2,248 | kg | 0 |
| 2 | Products trubopr.4 QNC DN>=100 | Unit water demineralization plant in the 10UMA building (10UMX). Spent resins from CPP regeneration and flushing system pipelines (10LDP). Filter pipi | 03.05.2025 | 03.05.2025 | DAP | RU | — | 22000000 | 166 | 254 | kg | 0 |
| 3 | Supports and suspensions of pipelines n.d. 4kl. | 10URS Modular Pumping Station. Process piping for the cooling water system serving non-critical loads. Metal bracket for securing the pressure relief | 02.04.2026 | 02.04.2026 | DAP | RU | — | 22000000 | 166 | 746,88 | kg | 0 |
| 4 | Supports and suspensions of pipelines n.d. 4kl. | 10URS Modular Pumping Station. Process piping for the cooling water system serving non-critical loads. Metal bracket for securing the pressure relief | 02.04.2026 | 02.04.2026 | DAP | RU | — | 22000000 | 166 | 1 120,32 | kg | 0 |
| 5 | Piping products 4 QNC DN<100 | Unit water demineralization plant in the 10UMA building (10UMX). Self-contained demineralizing plant system pipelines (10LDB) | 03.05.2025 | 03.05.2025 | DAP | RU | — | 22000000 | 166 | 42,824 | kg | 0 |
| 6 | Supports and suspensions of pipelines n.d. 4kl. | Unit water demineralization plant in the 10UMA building (10UMX). Self-contained demineralizing plant system pipelines (10LDB). | 03.05.2025 | 03.05.2025 | DAP | RU | — | 22000000 | 166 | 34,59 | kg | 0 |
| 7 | Piping products DN>=100 angles. | Intermediate diesel fuel storage (23UEJ). Fuel system pipelines | 02.04.2026 | 02.04.2026 | DAP | RU | — | 22000000 | 166 | 8,6 | kg | 0 |
| 8 | Piping products 4 QNC DN<100 | Turbine building (20UMA). Pipelines of secondary circuit equipment and pipelines hydraulic tests system PoP<2.2 Mpa RPR.0903.00UMA.LWB.TM.EC.2925. | 02.04.2026 | 02.04.2026 | DAP | RU | — | 22000000 | 166 | 2,248 | kg | 0 |
| 9 | Products trubopr.4 QNC DN>=100 | Unit condensate polishing plant in 20UMA building (20UMX). Pipelines of CPP spent resins regeneration and flushing system (20LDP). Pipework of the fil | 03.03.2026 | 03.03.2026 | DAP | RU | — | 22000000 | 166 | 254 | kg | 0 |
| 10 | Supports and suspensions of pipelines n.d. 4kl. | Unit pump station (20URS). Automatic fire fighting facilities | 26.01.2026 | 26.01.2026 | DAP | RU | — | 22000000 | 166 | 65,91 | kg | 0 |
| 11 | Piping products 4 QNC DN<100 | Unit pump station (20URS). Automatic fire fighting facilities | 26.01.2026 | 26.01.2026 | DAP | RU | — | 22000000 | 166 | 96,11 | kg | 0 |
| 12 | Products of pipelines V.D. 4 QNC DN<100 | Turbine building (20UMA). Automatic finely-dispersed water fire-fighting plants system SGK35. Pipeline with shaped parts for the SGK system | 02.04.2026 | 02.04.2026 | DAP | RU | — | 22000000 | 166 | 2 404,454 | kg | 0 |
| 13 | Supports and suspensions of pipelines n.d.4kl | Turbine building (20UMA). Automatic finely-dispersed water fire-fighting plants system SGK35. Level-adjusted supports and metal structure | 02.04.2026 | 02.04.2026 | DAP | RU | — | 22000000 | 166 | 2 205,642 | kg | 0 |
| 14 | Pipe supports. special channels | Reactor building (20UJA). Active sewage pipelines (pressure part) (KTH) | 02.04.2026 | 02.04.2026 | DAP | RU | — | 22000000 | 166 | 6,072 | kg | 0 |
| 15 | Pipe supports. special channels | Reactor building (20UJA). Active sewage pipelines (pressure part) (KTH). | 02.04.2026 | 02.04.2026 | DAP | RU | — | 22000000 | 166 | 11,88 | kg | 0 |
| 16 | Supports and suspensions of pipelines | Reactor building (20UJA). Primary circuit drain and controlled leaks pipelines (KTA) | 26.09.2022 | 26.09.2022 | DAP | RU | — | 22000000 | 166 | 0,16 | kg | 0 |
| 17 | Supports and suspensions of pipelines | Reactor building (20UJA). Primary circuit drain and controlled leaks pipelines (KTA). Pop < 2,2 MPa. L8-522.002-00 Eye (4psc) | 26.09.2022 | 26.09.2022 | DAP | RU | — | 22000000 | 166 | 0,08 | kg | 0 |
| 18 | Supports and suspensions of pipelines | Reactor building (20UJA). Reactor coolant pump pipework (JEB10). L8-522.003-00 Lug (2 psc) | 03.10.2025 | 03.10.2025 | DAP | RU | — | 22000000 | 166 | 0,16 | kg | 0 |
| 19 | Supports and suspensions of pipelines | Reactor building (20UJA). Reactor coolant pump pipework (JEB10). L8-522.002-00 Eye (4 psc) | 03.10.2025 | 03.10.2025 | DAP | RU | — | 22000000 | 166 | 0,08 | kg | 0 |
| 20 | Supports and suspensions of pipelines n.d. 4kl. | 20URS Modular Pumping Station. Process piping for the cooling water system serving non-critical loads. Metal bracket for securing the pressure relief | 27.05.2026 | 27.05.2026 | DAP | RU | — | 22000000 | 166 | 746,88 | kg | 0 |