| 1. |
Dismantling the control valve (4 pcs) |
| 2. |
Installation of the control valve (4 pcs) |
| 3. |
Dismantling of the upper and lower drainage and distribution system (4 pcs) |
| 4. |
Installation of the upper and lower drainage and distribution system (4 pcs) |
| 5. |
Unloading of used ion exchange resin - (softening system ) (2 pcs) |
| 6. |
Unloading of the filter material - (de-icing and clarification system ) (2 pcs) |
| 7. |
Flushing the housing and system (4 pcs) |
| 8. |
Loading of filter material - (system of de-icing and clarification of water ) (2 pcs) |
| 9. |
Loading of ion-exchange resin - (softening system ) (2 pcs) |
| 10. |
Programming the control valve (4 pcs) |