| No. | Name | Name (Eng) | Scheduled delivery date | Delivery start date | Incoterms code | Destination country | OKEI code | Quantity | Unit of measure | Number of bidders |
| 1 | Installation of diesel generator emergency power supply system P=6500KW U=10500V pnom=750ob/min IP23 Current=variable phase=3 f=50Hz 12320x3840x5040mm ITT PKS2.B.P000.&.0UBS&&&&&&&&.021.SG.0001.R B04 2 I QA2 | Diesel generator set of standby diesel generator station, train 4 | 09.07.2029 | 09.07.2029 | DAP | HU | 796 | 1 | pcs | 1 |
| 2 | Installation of diesel generator emergency power supply system P=6500KW U=10500V pnom=750ob/min IP23 Current=variable phase=3 f=50Hz 12320x3840x5040mm ITT PKS2.B.P000.&.0UBS&&&&&&&&.021.SG.0001.R B04 2 I QA2 | Diesel generator set of standby diesel generator station, train 4 | 09.07.2029 | 09.07.2029 | DAP | HU | 796 | 1 | pcs | 1 |
| 3 | Installation of diesel generator emergency power supply system P=6500KW U=10500V pnom=750ob/min IP23 Current=variable phase=3 f=50Hz 12320x3840x5040mm ITT PKS2.B.P000.&.0UBS&&&&&&&&.021.SG.0001.R B04 2 I QA2 | Diesel generator set of standby diesel generator station, train 4 | 09.07.2029 | 09.07.2029 | DAP | HU | 796 | 1 | pcs | 1 |
| 4 | Installation of diesel generator emergency power supply system P=6500KW U=10500V pnom=750ob/min IP23 Current=variable phase=3 f=50Hz 12320x3840x5040mm ITT PKS2.B.P000.&.0UBS&&&&&&&&.021.SG.0001.R B04 2 I QA2 | Diesel generator set of standby diesel generator station, train 4 | 09.07.2029 | 09.07.2029 | DAP | HU | 796 | 1 | pcs | 1 |
| 5 | Diesel generator set P=6500KW U=10500V pnom=750ob/min IP23 Current =variable phase =3 f=50Hz 10470x3100x5040mm ITT PKS2.B.P000.&.2UBN&&&&&&&&.021.SG.0001.R B04 3 QA2 | Diesel generator set for power supply of safety-related normal operation auxiliary consumers, train 6 | 05.10.2029 | 05.10.2029 | DAP | HU | 796 | 1 | pcs | 1 |
| 6 | Diesel generator set P=6500KW U=10500V pnom=750ob/min IP23 Current =variable phase =3 f=50Hz 10470x3100x5040mm ITT PKS2.B.P000.&.2UBN&&&&&&&&.021.SG.0001.R B04 3 QA2 | Diesel generator set for power supply of safety-related normal operation auxiliary consumers, train 6 | 10.06.2029 | 10.06.2029 | DAP | HU | 796 | 1 | pcs | 1 |
| 7 | Installation of diesel generator emergency power supply system P=6500KW U=10500V pnom=750ob/min IP23 Current=variable phase=3 f=50Hz 12320x3840x5040mm ITT PKS2.B.P000.&.0UBS&&&&&&&&.021.SG.0001.R B04 2 I QA2 | Diesel generator set of standby diesel generator station, train 4 | 11.07.2030 | 11.07.2030 | DAP | HU | 796 | 1 | pcs | 1 |
| 8 | Installation of diesel generator emergency power supply system P=6500KW U=10500V pnom=750ob/min IP23 Current=variable phase=3 f=50Hz 12320x3840x5040mm ITT PKS2.B.P000.&.0UBS&&&&&&&&.021.SG.0001.R B04 2 I QA2 | Diesel generator set of standby diesel generator station, train 4 | 11.07.2030 | 11.07.2030 | DAP | HU | 796 | 1 | pcs | 1 |
| 9 | Installation of diesel generator emergency power supply system P=6500KW U=10500V pnom=750ob/min IP23 Current=variable phase=3 f=50Hz 12320x3840x5040mm ITT PKS2.B.P000.&.0UBS&&&&&&&&.021.SG.0001.R B04 2 I QA2 | Diesel generator set of standby diesel generator station, train 4 | 11.07.2030 | 11.07.2030 | DAP | HU | 796 | 1 | pcs | 1 |
| 10 | Installation of diesel generator emergency power supply system P=6500KW U=10500V pnom=750ob/min IP23 Current=variable phase=3 f=50Hz 12320x3840x5040mm ITT PKS2.B.P000.&.0UBS&&&&&&&&.021.SG.0001.R B04 2 I QA2 | Diesel generator set of standby diesel generator station, train 4 | 11.07.2030 | 11.07.2030 | DAP | HU | 796 | 1 | pcs | 1 |
| 11 | Diesel generator set P=6500KW U=10500V pnom=750ob/min IP23 Current =variable phase =3 f=50Hz 10470x3100x5040mm ITT PKS2.B.P000.&.2UBN&&&&&&&&.021.SG.0001.R B04 3 QA2 | Diesel generator set for power supply of safety-related normal operation auxiliary consumers, train 6 | 29.10.2030 | 29.10.2030 | DAP | HU | 796 | 1 | pcs | 1 |
| 12 | Diesel generator set P=6500KW U=10500V pnom=750ob/min IP23 Current =variable phase =3 f=50Hz 10470x3100x5040mm ITT PKS2.B.P000.&.2UBN&&&&&&&&.021.SG.0001.R B04 3 QA2 | Diesel generator set for power supply of safety-related normal operation auxiliary consumers, train 6 | 12.06.2030 | 12.06.2030 | DAP | HU | 796 | 1 | pcs | 1 |
| 13 | Installation supervision | Installation Supervision | 05.10.2029 | 10.06.2029 | — | HU | UDF | 1 | - | 1 |
| 14 | Installation supervision | Installation Supervision | 29.10.2030 | 12.06.2030 | — | HU | UDF | 1 | - | 1 |