Execution of a complex of works on the installation of the roof, sandwich panels of building No. 11 "Material Warehouse" at the facility: "Plant for the production of cells, modules, packs and stationary systems based on lithium-ion cells 4GWh in...

No.NameScheduled delivery dateDelivery start dateDestination countryDelivery regionOKTMO CodeQuantityUnit of measureNumber of bidders
1The device of a prefabricated screed from GVLV plates 10 mm thick, m2 (p.p. 1.1)22.12.202610.11.2026RU—277000000001EP0
2The device of a film vapor barrier in one layer, m2 (p.p. 2.1-2.2)22.12.202610.11.2026RU—277000000001EP0
3Thermal insulation device from XPS plates PENOPLEX BASE 100 mm thick with a slope-forming layer PENOPLEX BASE SLOPE, m2 (p.p. 3.1-3.20)22.12.202610.11.2026RU—277000000001EP0
4The device of the separating layer from the glass wool PLASTFOIL CANVAS in one layer, m2, (clause 4.1)22.12.202610.11.2026RU—277000000001EP0
5Waterproofing device of the main roof plane made of reinforced PVC membrane PLASTFOIL Classic with a thickness of 1.5 mm, m2 (p.p. 5.1)22.12.202610.11.2026RU—277000000001EP0
6The device of joining the PVC membrane to the sandwich panels of the parapet, m2 (p.p. 6.1-6.11)22.12.202610.11.2026RU—277000000001EP0
7Filling of the extreme corrugations of the profiled sheet with mineral wool insulation, m3 (item 7.1)22.12.202610.11.2026RU—277000000001EP0
8The device of a metal drainage system: straight pipe links, m (p.p. 8.1-8.2)22.12.202610.11.2026RU—277000000001EP0
9The device of the metal drainage system: knees, pcs (p.p. 9.1)22.12.202610.11.2026RU—277000000001EP0
10The device of the metal drainage system: funnels, pcs (p.p. 10.1-10.2)22.12.202610.11.2026RU—277000000001EP0
11Arrangement of gutters: suspended, m (p.p. 11.1-11.3)22.12.202610.11.2026RU—277000000001EP0
12Installation of PLASTFOIL STEPWAY footpaths on the roof surface, pcs (item 12.1)22.12.202610.11.2026RU—277000000001EP0
13Installation of parapet covers from FI-5 shaped products with FI-7 support elements, m (clauses 13.1-13.2)22.12.202610.11.2026RU—277000000001EP0
14The device of fire protection of the roof with non-combustible fiberglass FireProtect PVC, m2 (p.p. 14.1)22.12.202610.11.2026RU—277000000001EP0
15Sealing the passage of half-timbered racks through the roof with a PVC membrane with a thermal break device, pcs22.12.202610.11.2026RU—277000000001EP0
16The device of the deformation seam of the roof along the E axis with a PVC membrane and a sealing cord, m (p.p. 16.1)22.12.202610.11.2026RU—277000000001EP0
17Arrangement of nodes for the passage of roof ventilation shafts through the roof cake, m2 (p.p. 17.117.3)22.12.202610.11.2026RU—277000000001EP0
18Installation of profiled flooring H114-750-0.8 with polymer coating RAL 9003, m2 (p.p. 18.1)22.12.202610.11.2026RU—277000000001EP0
19Installation of exterior wall sandwich panels 120 mm thick, m2 (p.p. 19.1)22.12.202610.11.2026RU—277000000001EP0
20Installation of internal wall sandwich panels 120 mm thick, m2 (p.p. 20.1-20.2)22.12.202610.11.2026RU—277000000001EP0