Price monitoring request No. 3242239 
execution of development work on the topic: "Creation of a pilot plant for the production of polyanion cellulose"

execution of development work on the topic: "Creation of a pilot plant for the production of polyanion cellulose"

Purchasing items:
1. Проведение ОКР (1 )
Publication date:
Bids submission deadline
Bids can also be submitted after the expiry of the specified period. However, bidding organizer has the right not to consider the bids submitted after bids submission deadline.
:
10.03.2023 23:59
Last edited:28.02.2023 08:33
Responsible person:Robotov Robot Robotovich
Organizer (Initiator):JSC "AECC"
Additional info
Payment terms:The procedure for settlements between the Contractor and the Customer is carried out in stages: 1 The total cost of the first stage of OCD is _____________ (__________________) rubles 00 kopecks, VAT is not levied in

in accordance with clause 16.1 clause 3 of Article 149 of the Tax Code of the Russian Federation. The Customer pays the Contractor an advance in the amount of 30% of the cost of performing the first stage of the ROC. Advance payment amount _____________ (__________________) rubles

00 kopecks is paid by the Customer no earlier than 45 (forty-five) and no later than 55 (fifty-five) calendar days from the date of receipt by the Contractor from the Customer of the notification of the start of work on

to the first stage, on the basis of an invoice issued by the Contractor, provided that the Contractor provides security for the return of the specified advance amount. The remaining 70% of the cost of the first stage of OCD

in total _____________ (__________________) the Customer pays rubles 00 kopecks no earlier than 45 (forty-five) and no later than 55 (fifty-five) calendar days after signing by the Customer

the act of delivery and acceptance of the first stage of OCD. 2 The total cost of the second stage of OCD is _____________ (__________________) rubles 00 kopecks, VAT is not levied in accordance with clause 16.1 clause 3 of Article 149

The Tax Code of the Russian Federation. The Customer pays the Contractor an advance in the amount of 30% of the cost of performing the second stage of the ROC. Advance payment amount _____________ (__________________) rubles 00 kopecks is paid by the Customer in

the deadline is not earlier than 45 (forty-five) and not later than 55 (fifty-five) calendar days from the date of receipt by the Contractor from the Customer of the notification of the start of work on the second stage, based on the invoice,

issued by the Contractor, provided that the Contractor provides security for the return of the specified advance amount. The remaining 70 % of the cost of the second stage of OCD in the amount of _____________

(__________________) the Customer pays rubles 00 kopecks no earlier than 45 (forty-five) and no later than 55 (fifty-five) calendar days after the Customer signs the acceptance certificate

the second stage of OCD. 3 The total cost of the third stage of OCD is _____________ (__________________) rubles 00 kopecks, VAT is not levied in accordance with clause 16.1 of Clause 3 of Article 149 of the Tax Code of the Russian Federation. Customer

pays the Contractor an advance payment in the amount of 30% of the cost of performing the third stage of the OCD. Advance payment amount _____________ (__________________) rubles 00 kopecks are paid by the Customer no earlier than 45

(forty-five) and no later than 55 (fifty-five) calendar days from the date of receipt by the Contractor from the Customer of the notification of the start of work on the third stage, based on the invoice issued

By the Contractor, provided that the Contractor provides security for the return of the specified advance amount. The remaining 70 % of the cost of the third stage of OCD in the amount of _____________ (__________________)

The Customer pays rubles 00 kopecks no earlier than 45 (forty-five) and no later than 55 (fifty-five) calendar days after the Customer signs the acceptance certificate of the third stage of the ROC. 4

The total cost of the fourth stage of OCD is _____________ (__________________) rubles 00 kopecks, VAT is not levied in accordance with clause 16.1 of Clause 3 of Article 149 of the Tax Code of the Russian Federation. The customer pays

The contractor receives an advance payment in the amount of 30% of the cost of performing the fourth stage of OCD. Advance payment amount _____________ (__________________) rubles 00 kopecks are paid by the Customer no earlier than 45 (forty

five) and no later than 55 (fifty-five) calendar days from the date of receipt by the Contractor from the Customer of the notification of the start of work on the fourth stage, based on the invoice issued by the Contractor

provided that the Contractor provides security for the return of the specified advance amount. The remaining 70 % of the cost of the fourth stage of OCD in the amount of _____________ (__________________) rubles 00 kopecks

The Customer pays no earlier than 45 (forty-five) and no later than 55 (fifty-five) calendar days after the Customer signs the acceptance certificate of the fourth stage of the ROC. Advance payments

are subject to payment by the Customer only after he receives from the Contractor the fulfillment of obligations to return the Advance Payment in accordance with section 11 of this agreement.
Venue of bidding:This call for bids is carried out in e-form in Rosatom section of RTS-tender e-marketplace (www.rosatom.rts-tender.ru). Bidders' proposals are to be submitted in the form of an e-document.
Bid documentation provision procedure:Bid documentation is provided free of charge in the form of an e-document in Rosatom section of RTS-tender (www.rosatom.rts-tender.ru), starting from the date of announcing a call for bids.
Please note that this Prices Monitoring Request is a procedure aimed at enabling the Organizer to determine the maximum initial contract price for a call for bids to be held afterwards, and imposes no obligations on the Organizer as to entering into a contract.
 
 
 

 
Submitted bids
Status: archived.
Total: 1